Tech Report: PRIMO-SWELL System Mitigates Well Control Issues and Improves Completion Efficiency, Asia

55-bbl system mixes on site in 3.5 hours and enables full packer swelling in less than 20 hours for optimized gravel packing

PRIMO-SWELL System Mitigates Well Control Issues and Improves Completion Efficiency, Asia

Publication Date: 06/13/2017

A customer installed OptiPac Alternate Path openhole gravel-pack screens using fast oil-swellable packers to separate zones and provide sand control. The swell packers were expanded prior to pumping the gravel-pack job. In previous wells where this strategy was deployed, diesel was spotted to swell the packers, which created a U-tube effect that incurred NPT to address. Other drilling challenges included drilling fluid contamination and well control concerns.

A batch mixer on location mixed the PRIMO-SWELL oil-swellable-packer activation system formulated with PRIMO-VIS oil-swellable-packer activation fluid viscosifier for viscosity and WARP DRY high-density collodial suspension technology as a weighting agent. A series of laboratory tests demonstrated the required performance to the customer, and no annulus pressure spikes or stability issues were observed during swell packer expansion.




Related services and products

 
Request More Information