Challenge: Initiate production while permanent production facilities are under construction.

Solution: Implement standard Veloceti early production system with specifications suited to operator and field needs.

Results: Achieved initial 10,000-bbl/d production in less than 5 months from contract award to plant startup.

Products Used

Available-On-Demand Facility Enables Reaching First Production in Less Than 5 Months, Indonesia

Leased Veloceti early production system customized for sour oil initiates output at 10,000 bbl/d during central processing facility construction

Efficient deployment of equipment to enable early production

An operator in Indonesia sought a faster alternative to achieving first production from an onshore  sour oil field while a permanent production facility was under construction. With a goal of reaching 160,000 bbl/d during permanent production, the operator wanted to bring the block online earlier than planned. However, the block produces 26-API oil, and operations must take into consideration high  H2S volumes, safety, noise levels, environmental impact, and local vendor requirements.

Cooperation on facility design to accelerate operational efficiency

To reach initial production sooner, the operator and Schlumberger worked together to engineer and approve the design of the early production facility best suited to the operational  specifications and the field itself. The Veloceti system design was used—envisioned by Schlumberger and designed to meet all regulatory requirements and international standards—with components added to meet the field's specific needs. The combination of knowledge of local operating procedures paired with Schlumberger's ability to effectively engineer, manufacture, and procure equipment in  the region resulted in a timeline from contract award to first production of less than 5 months.

overflow image
Production was initiated in less than 5 months with a customized facility design of the Veloceti early production system.

10,000-bbl/d early production to bridge to permanent facility

Realized with the Veloceti early production system, our approach to facility and field development provided fiscal metering for the block's 10,000-bbl/d production during completion of the permanent facilities. Positive cash flow was quickly generated to finance and sustain ongoing and upcoming field development, which was optimized through enhanced reservoir knowledge from early production. Once the long-term goal of the 160,000-bbl/d production facility was met, the lease for the Velocity system was terminated and the facility demobilized. In this era of uncertainty, agility is a necessity, and the Veloceti system helps operators maximize their velocity to cash flow.