A mature onshore gas storage well drilled in 1984 had become unavailable for gas storage service following loss of mechanical integrity in the original gravel pack completion, resulting in formation sand production. The selected workover strategy involved removing the original completion, permanently abandoning the lower section of the existing borehole, and drilling a sidetrack into the same storage interval with a new gravel pack completion.

Before executing the abandonment and sidetrack programme, the integrity of the retained well architecture had to be established. However, no historical cement evaluation data were available for either the inner 7-in. production casing or the outer 9 5/8-in. intermediate casing, and no recent corrosion data were available for the 7-in. casing. Because the 7-in. casing was to remain in place and support the planned sidetrack operation, its mechanical condition and cement integrity required confirmation. Conventional direct evaluation of the annulus behind the 9 5/8-in. casing was not possible while the 7-in. casing remained in place. The objectives were therefore to assess the casing condition and cement integrity of the retained 7-in. string and evaluate annular isolation behind the inaccessible 9 5/8-in. casing. 

The dual string evaluation combined multimodality ultrasonic imaging and deep array multimode sonic measurements, followed by an independent 56-finger caliper survey. The ultrasonic and multifinger caliper measurements evaluated the internal geometry and remaining wall thickness of the inner 7-in. casing. Acoustic impedance, flexural attenuation, conventional CBL/VDL, and Third Interface Echo measurements characterised the material behind the 7-in. casing and the geometry between the 7-in. and 9 5/8-in. strings. Low frequency orthogonal dipole dispersion analysis provided separate bond evaluations for the annuli behind the 7-in. and 9 5/8-in. casings, enabling dual casing barrier evaluation without removing the inner casing. Third interface echo measurements processing also provided first annulus acoustic velocity and pipe to pipe standoff. Formation compressional and shear responses were extracted from the sonic dataset where they could be separated reliably from casing related modes.

The casing inspection measurements showed no significant metal loss or deformation that would prevent retention of the 7-in. casing for the sidetrack operation. The interpreted cement top behind the 7-in. casing was in close agreement with the historical value and was supported by the ultrasonic, CBL/VDL, and dipole responses. Across the planned sidetrack setting interval, the low frequency orthogonal dipole bond indices and CBL/VDL indicated good bond, whereas the high frequency ultrasonic measurements indicated poor interfacial coupling consistent with dry microannulus. Integration of the ultrasonic, CBL/VDL, and dipole responses supported the presence of cement beyond the poorly coupled casing–cement interface rather than an absence of cement.

The second annulus evaluation indicated cement to surface and generally good bond behind the 9 5/8in. casing, resolving the principal uncertainty created by the absence of historical cement evaluation data. The otherwise inaccessible second annulus was evaluated while the 7-in. casing remained in place, avoiding removal of the inner string solely to obtain cement bond information behind the outer casing. Third interface echo (TIE) derived annular acoustic velocity and casing standoff provided additional information relevant to future cut and pull, dual string cutting, and annular fluid circulation planning. Formation acoustic responses recovered from the sonic dataset provided additional information for geomechanical, petrophysical, seismic calibration to support sidetrack planning.

The case demonstrates the value of dual string barrier evaluation for mature wells where cement bond information is required behind two casing strings before abandonment and sidetrack operations. The workflow evaluated bond behind both the 7-in. and 9 5/8-in. casings while the inner string remained in place and distinguished poor interfacial coupling associated with dry microannulus from an absence of cement. The same evaluation provided inner casing condition, annular fluid typing, casing position, and formation acoustic information to support intervention and sidetrack planning.