Liwan Gas Project | SLB

Liwan Gas Project

Published: 05/06/2013

Premium
Schlumberger Oilfield Services

Husky Energy installed 14 "frac-pack" lower completions, 10 sub-sea horizontal trees, and 7 upper completions utilizing two 6-th generation deep water semi-submersibles in Block 29/26 of the Pearl River Marine Basin (PRMB) South China Sea between June 2011 and January 2013. On average, the lower completions, tree installation and upper completions required, 12 days, 2 day and 24 days, respectively. The water depth ranged from 650 m to 1450 m.

THIS ITEM IS PREMIUM CONTENT. TO ACCESS THE FULL CONTENT, SIGN IN OR REGISTER BELOW.
Sign in or register