Integrated Services Cut Completion Time by 40%

Published: 12/01/2006

Blue hero texture

Increasing gas production

In January 1994, a PEMEX task force developed a new approach for significantly increasing gas production from the Burgos basin of northern Mexico. PEMEX wanted to enhance operating resources and capabilities by using integrated service companies to meet the high demand for natural gas in industry and power generation in Mexico. PEMEX contracted with the IPM team in 1997 on the first integrated project. The project plan called for the IPM team to acquire 3D seismic data on 250 mi2, perform 2 integrated reservoir studies, drill 31 wells, and construct a gas-gathering station and 4 gas compression plants. The IPM team completed the work in 11 months.

Integrating services and full project management

The relationship and trust between PEMEX and IPM have grown since that first project, as has the scope of IPM responsibilities: from providing integrated services to full project management-planning through implementation. IPM is currently undertaking the fifth major integrated project contract in the Burgos basin.

Field Studies Guide PEMEX Burgos Basin Natural Gas Drilling Project
Geographic location of the Burgos Basin.

In the latest contract, IPM will provide all engineering project management and related services to bring 310 wells on line. IPM responsibilities will include designing the drilling programs; providing and managing rigs; and supervising and performing completion, perforating, fracturing, and well-testing operations. In addition, the IPM team will develop all engineering plans for production enhancement, and manage and execute wellsite supervision, directional drilling, data collection, drilling fluids selection, and flowline installation. The IPM team will also supervise

Field Studies Guide PEMEX Burgos Basin Natural Gas Drilling Project

and manage all logistics, waste management, and construction of access ways and wellsites.

From January 2003 to January 2004, IPM completed 72 wells, performed 93 fracture jobs, and tested 122 intervals with a collective initial production rate of 5.35 million m3/d [189 MMcf/d].

In January 1994, a PEMEX task force developed a new approach for significantly increasing gas production from the Burgos basin of northern Mexico. PEMEX wanted to enhance operating resources and capabilities by using integrated service companies to meet the high demand for natural gas in industry and power generation in Mexico.

Location
Mexico, North America, Onshore
Details

Challenge: PEMEX wanted to enhance operating resources and capabilities by using Schlumberger Integrated Project Management (IPM) to increase gas production from the Burgos basin of northern Mexico.

Solution: IPM provided rig provision and management; well drilling; directional drilling; drilling fluids; cementing; logging; completion and stimulation; production enhancement and logistics; and civil works.

Results: Schlumberger delivered 375 wells over 5 contracts. Well completion times were reduced by 40%. Wells were efficiently stimulated using the PowerSTIM well optimization service, increasing productivity by 5% to 10% per well. New drilling opportunities were identified and a better understanding of reservoir structure and stratigraphy was developed.