Treatment Reduces ESP Failure Rate

Published: 10/01/2007

Blue hero texture
Graph: Treatment reduces ESP failure rate
Graph:  Treatment reduces ESP failure rate  - Well workover required after 3 months production prior to Schlumberger solution.
Well workover required after 3 months production prior to Schlumberger solution. Uninterrupted production for more than 9 months after scale and proppant flowback solution.
Location
Indonesia, Asia, Onshore
Details

Challenge: Scale buildup and unexpected proppant flowback account for 73% of ESP failures.

Solution: Schlumberger designed a single stage treatment that integrates ScaleFRAC scale inhibitor service and PropNET hydraulic fracturing proppant flowback control technology.

Results: Uninterrupted production for more than 9 months after scale and proppant flowback solution.

Products Used