Naturally fractured limestone

Depleted zone depth, m [ft]
1,400 [4,600]

Initial mud weight, g/cm3 [lbm/galUS]
1.08 [9.0]

Loss-control mud weight, g/cm3 [lbm/galUS]
1.03 [8.6]

Sidetrack kickof point, m [ft]
1,050 [3,400]

Background
An operator was preparing to abandon a depleted zone and then sidetrack the well at a shallower depth to access additional reserves. Immediately after the depleted zone’s packer was milled, the well incurred circulation losses of 3.2–4.8 m3/h [20–30 bbl/h] across the perforations. The mud was loaded with sawdust and rice husk, reducing density to maintain the fluid level in the well for cementing.
Products Used

Cement Plug with CemNET Technology Enables Sidetrack After Lost Circulation Event, Pakistan

Low-density LiteCRETE slurry isolates depleted zone for abandonment

overflow image
To deliver lightweight cement with high compressive strength and avoid losses, Schlumberger designed and delivered a 2.4-m3 [15-bbl] cement plug comprising LiteCRETE slurry at 1.44 g/cm3 [12 lbm/galUS] and CemNET technology at 4.3 kg/m3 [1.5 lbm/bbl]. No losses were seen after the plug hit the perforations, and the well had full returns during reverse circulation. After setting, the plug was tagged with 5-t weight on bit and the well pressure tested to 6.9 MPa [1,000 psi].